S.No Description Date
1 Signing MoU with GoN 02.03.2008
2 Completion of Survery & Investigation Work 15.01.2011
3 Submission of DPR of Project to CEA 31.03.2011
4 Submission of Transmission line DPR to CEA 05.04.2011
5 Completing Public Hearing 24.02.2013
6 SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered. 25.04.2013
7 Vetting of DPR of Project by CEA 09.06.2013
8 Vetting of Transmission Line by CEA 20.06.2014
9 Signing PDA with GoN 25.11.2014
10 EIA approval by GoN 12.08.2015
11 MoU between SAPDC &DoR 05.01.2016
12 Agreement with DoR 29.05.2016
13 PIB approval 20.09.2016
14 RAP approval for Project 20.02.2017
15 CCEA Approval 22.02.2017
16 LoA of Civil Package-I 22.09.2017
17 LoA of Civil Package-II 19.03.2018
18 LoA of HM Package 11.04.2018
19 LoA of EM Package 30.04.2018
20 LoA of Tower Pkgs. TW01 & TW02 08.12.2019
21 LoA of Substation Package 31.08.2020
22 LoA of Conductor Pkgs. CD01 & CD02 23.12.2020