1 |
Signing MoU with GoN |
02.03.2008 |
2 |
Completion of Survery & Investigation Work |
15.01.2011 |
3 |
Submission of DPR of Project to CEA |
31.03.2011 |
4 |
Submission of Transmission line DPR to CEA |
05.04.2011 |
5 |
Completing Public Hearing |
24.02.2013 |
6 |
SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC) established & Registered. |
25.04.2013 |
7 |
Vetting of DPR of Project by CEA |
09.06.2013 |
8 |
Vetting of Transmission Line by CEA |
20.06.2014 |
9 |
Signing PDA with GoN |
25.11.2014 |
10 |
EIA approval by GoN |
12.08.2015 |
11 |
MoU between SAPDC &DoR |
05.01.2016 |
12 |
Agreement with DoR |
29.05.2016 |
13 |
PIB approval |
20.09.2016 |
14 |
RAP approval for Project |
20.02.2017 |
15 |
CCEA Approval |
22.02.2017 |
16 |
LoA of Civil Package-I |
22.09.2017 |
17 |
LoA of Civil Package-II |
19.03.2018 |
18 |
LoA of HM Package |
11.04.2018 |
19 |
LoA of EM Package |
30.04.2018 |
20 |
LoA of Tower Pkgs. TW01 & TW02 |
08.12.2019 |
21 |
LoA of Substation Package |
31.08.2020 |
22 |
LoA of Conductor Pkgs. CD01 & CD02 |
23.12.2020 |