1 |
Annual lawn maintenance & flower beds etc. of office and residential complex of SAPDC, Arun-3 at Tumlingtar, for a period of two years. |
18/09/2024 |
10/12/2024 |
M/S Sagarmatha Muliti Service Pvt. Ltd., Minbhawan-31, Kathmandu, Nepal. |
NPR 7986201/- |
Through Open Tender |
2 |
Construction of Road from Kuwapani Ch.0+000 KM to Tade (Ward-3) Ch. 3+095 Km at Chichila Rural Muncipality- 01 & 03, Distt. Sankhuwasabha, Nepal under Local Benefit Sharing Plan (LBSP) of Arun-3 HEP |
06.05.2024 |
17.11.2024 |
M/s Rani Dhunga Nirman Sewa Pvt. Ltd. Khadbari-03, Sankhuwasabha, Nepal |
NPR 68,82,728.32/- |
|
3 |
Construction of Road from Kharshu Ch.0+000 Km to Fakadam Ch.3+035 Km at Chichila Rural Muncipality-03, Distt. Sankhuwasabha, Nepal under Local Benefit Sharing Plan (LBSP) of Arun-3 HEP |
06.05.2024 |
17.11.2024 |
M/s Arun Barun Nirman Sewa Company Pvt. Ltd., Chichila RM-03, Sankhuwasabha, Nepal |
NPR 93,26,836 |
|
4 |
Observing discharge and silt data at DAM G&D site (Uwagaon) of Arun-3 HEP (900MW), Nepal for a period of Two years. |
13/08/2024 |
04/12/2024 |
M/s Innovative Engineering Services Pvt. Ltd., Lalitpur, Nepal. |
NPR 44,90,000/- |
Through Open Tender |
5 |
Construction of store building (unit-I & unit-II), office building, security building, boundary wall with entrance gate, concrete road and concrete platform (open store) at Mithila Muncipality, Dhalkebar Distt. Dhanusha, Nepal |
21-05-2024 |
25-10-204 |
M/s Chainlink Engineering Pvt Ltd., Balkot-1, Bhaktapur, Nepal |
NPR 2,33,88,643/- |
|
6 |
Hydro-Mechanical Works - TRT Gates and associated equipment for Arun-3 HEP and associated equipment for Lower Arun HEP in Sankhuwasabha Distt. of Nepal |
13/02/2023 |
01/10/2024 |
M/s S.S Fabricators & Manufacturers Pvt.Ltd. BG1 & BG2, Swami Sadan Apartment, Civil Lines, Nagpur-440 001. |
26,70,00,000/- |
|
7 |
Restoration of Water Supply to Village / Tole Mulgaun, Amrang, Ward no. 5 Makalu Rural Municipality, Nepal |
09-04-2024 |
14-08-2024 |
M/s Bhagawati Nirman Sewa, Chichila RM-1, Sankhuwasabha, Nepal |
NPR 14,12,881.80/- |
|
8 |
Construction of Prefabricated panels Transit camp Building at Phaksinda Colony near Dam site of Arun-3 HEP, Sankhuwasabha Distt. Nepal, including supply, erection & fixing of Civil Items, Water supply, Sanitary, Electrical and Sewerage works complete in all respect as per site, drawings and Technical Specifications |
13 August 2018 |
02 Dec. 2018 |
M/s Bright Multi Construction Pvt. Ltd., Pokhari Chauri-9, Kavreplanchok, Nepal |
1,48,85,976/- |
|
9 |
Construction of cement concrete road from Tumlingtar airport to Gidde on Manokamna temple road via Tumlingtar complex of Arun-3 HEP, Nepal (RD 0.600 km to 2.385 km) as per site, drawings and Technical Specifications |
13 August 2018 |
30 Nov. 2018 |
M/s Koshi & Neupane Nirman Sewa Pvt. Ltd., Ward No. 10, New Baneshwor, Kathmandu, Nepal |
1,82,73,340/- |
|
10 |
Plastering/Painting of existing boundary wall around SAPDC complex of Arun-3 HEP at Tumlingtar |
|
05 Nov. 2018 |
M/s Khampache Sherpa Nirman Sewa Pvt. Ltd, Chabahil-7,Kathmandu,Nepal |
18,21,777 /- |
|
11 |
Website Development for SJVN Arun-3 Power Development Company Pvt Ltd (SAPDC). |
21 June 2018 |
27 Sept. 2018 |
M/s Cyberlink Pvt. Ltd, Pako, Newroad Kathmandu, Nepal |
5,33,360 /- |
- |